Critical Path Method: How to Find the Critical Path, With a Construction Example
Critical Path Method: How to Find the Critical Path, With a Construction Example
Every project has a chain of work that decides when it can finish. The critical path method (CPM) is how you find that chain. Once you know it, you know which delays will move the finish date and which ones you can absorb. This guide works through a small building example by hand, so that you understand what scheduling software is doing when it marks activities as critical.
The Short Version
- The critical path is the longest chain of linked activities from start to finish. Its length is the shortest time the project can take with that logic and those durations.
- A forward pass gives the earliest each activity can start and finish.
- A backward pass gives the latest each can start and finish without delaying the project.
- Total float is the difference between the two. In a simple network, activities with zero float are critical.
- The critical path can change when another activity slips by more than its float.
What You Need Before You Start
- A list of activities, taken from the way the work is broken down.
- A duration for each activity, based on quantity, crew and productivity.
- The logic between them: which activity must finish before another can start.
This example uses only finish to start links, with no lags, and counts working days from day 0.
The Example Project
Nine activities from part of a small building. The durations are made up for teaching.
- A. Excavation: 4 days, starts the project
- B. Footings: 6 days, after A
- C. Underground drainage: 3 days, after A
- D. Backfill and plinth: 2 days, after B and C
- E. Structural frame: 12 days, after D
- F. Fabricate doors and windows: 15 days, after A
- G. Deliver doors and windows: 2 days, after F
- H. Masonry: 8 days, after E
- I. Fix doors and windows: 3 days, after G and H
Step 1: Forward Pass
Work from the start to the end. Early finish is early start plus duration. An activity's early start is the largest early finish among the activities before it.
- A: early start 0, early finish 4
- B: 4 to 10
- C: 4 to 7
- D: 10 to 12, because it waits for B, which finishes later than C
- E: 12 to 24
- F: 4 to 19
- G: 19 to 21
- H: 24 to 32
- I: 32 to 35, because it waits for H, which finishes later than G
The project takes 35 working days.
Step 2: Backward Pass
Now work from the end to the start, beginning with a late finish of 35. Late start is late finish minus duration. An activity's late finish is the smallest late start among the activities after it. Each line shows late start to late finish.
- I: 32 to 35
- H: 24 to 32
- G: 30 to 32
- F: 15 to 30
- E: 12 to 24
- D: 10 to 12
- C: 7 to 10
- B: 4 to 10
- A: 0 to 4, set by B, which has the earliest late start of the three activities that follow A
Step 3: Calculate Float
- Total float = late start - early start. It is how long an activity can slip without delaying the project.
- Free float = earliest early start among the following activities - early finish of this one. It is how long an activity can slip without moving the early start of any activity that follows. For the last activity, use the project finish.
In this example:
- A, B, D, E, H and I: total float 0, free float 0
- C: total float 3, free float 3
- F: total float 11, free float 0
- G: total float 11, free float 11
Look at F. It has 11 days of total float but no free float: if fabrication slips even one day, delivery moves one day too. The 11 days are shared by F and G. They do not get 11 days each.
The Critical Path in This Example
The critical path is A, B, D, E, H, I. Add the durations: 4 + 6 + 2 + 12 + 8 + 3 = 35 days, which matches the forward pass. If any of these activities takes a day longer, and nothing else changes, the project finishes a day later.
What Happens When Something Slips
Fabrication takes 27 days instead of 15. F has slipped 12 days, one more than its float of 11. The project now takes 36 days, and the critical path moves to A, F, G, I. The frame, which was critical before, now has one day of float.
Drainage takes 6 days instead of 3. C uses all 3 days of its float. The project still takes 35 days, but C is now critical as well, so there are two critical chains between excavation and the plinth.
The lesson is to watch near critical activities too, and to recalculate the schedule every time you update progress.
Critical Path in Primavera P6 and MS Project
Software does the same passes, using calendars and dates. Check how it has been told to define "critical":
- Primavera P6 can mark activities as critical either by total float at or below a value you set, or by longest path, which is the driving sequence that sets the project finish date.
- Microsoft Project marks a task as critical when its total slack is at or below a set value. The default is 0 days, and the setting is under File, Options, Advanced. Slack is its word for float.
Because of these settings, two files with the same logic can mark different activities as critical. Calendars, constraints and lags can also give float values that look strange until you trace them. For more on choosing between the two tools, see Primavera vs MS Project.
Common Mistakes
- Leaving out links, which gives activities false float and hides the real critical path.
- Using date constraints where a logical link is needed.
- Treating total float as time that each activity owns.
- Watching only the critical activities and ignoring those with a day or two of float.
- Not updating the schedule with actual progress.
- Trusting the software's critical path without checking that the logic matches how the work will be built.
Learn It on a Real Schedule
Doing one network by hand makes the idea clear. A real building schedule has repeating floors, calendars, resources and many more links. Protrainy's Building Planning Combo covers both Primavera P6 and Microsoft Project for construction. It is instructor-led, taught in Hinglish, currently Rs 14,999 and rated 4.8 out of 5. Ask for the syllabus and the hours given to each tool before you enroll.
Our guide to the Building Planning Combo compares it with buying one course at a time. If you are still deciding on the role, read what to learn to become a planning engineer.
Next Step
Copy the nine activities onto paper and work out both passes without looking at the answers. Then change masonry to 10 days and see what moves. For any question, write to support@protrainy.com.