Bar Bending Schedule: How to Prepare a BBS, With Worked Examples
Bar Bending Schedule: How to Prepare a BBS, With Worked Examples
A bar bending schedule (BBS) is a table that lists the reinforcement bars in a structure: where each one goes, its shape and diameter, how many are needed and how long each must be cut. The steel yard cuts and bends from it, the store orders from it and the billing engineer checks quantities against it. This guide shows what a BBS contains, how to prepare one and how the numbers work out for a beam stirrup and a set of footing bars.
The Short Version
- A BBS lists every bar by location, shape, size, number and length.
- The common site method for cutting length is the outer dimensions, plus hook extensions, minus bend deductions.
- Weight per metre of a round bar is d × d / 162.2 kg, where d is the diameter in mm.
- IS 2502 says cutting lengths are to be given to the next whole 25 mm.
- Your drawings and project specification come first. The figures below are teaching examples.
What a Bar Bending Schedule Contains
IS 2502, the code of practice for bending and fixing reinforcement bars, gives a standard form with these columns:
- Location of the member
- Mark designation, which also goes on the label tied to the bars
- Size and type of bar
- Number of sets
- Number per set
- Total number
- Length
- Shape, with its dimensions
Site schedules often add the drawing number and revision, total length, weight per metre and total weight.
What You Need Before You Start
- The latest revision of the structural drawings, including the general notes and bar details.
- The nominal cover. IS 456 says it must not be less than the bar diameter. For durability, its minimum values are 20 mm for mild exposure, 30 mm for moderate, 45 mm for severe, 50 mm for very severe and 75 mm for extreme, with a few exceptions listed in the code.
- Extra cover rules for some members. Longitudinal bars in columns generally need at least 40 mm, with an exception for small columns, and footings need at least 50 mm.
- Lap and anchorage lengths, as given on the drawings.
- The grade of steel to be used.
How to Prepare a BBS, Step by Step
- List every different bar on the drawing and give each one a mark.
- Sketch its shape and work out its dimensions after taking off the cover.
- Add hook extensions, upturned ends and laps where the drawing calls for them.
- Subtract the bend deductions.
- Round the cutting length up to the next 25 mm.
- Count the bars. For evenly spaced bars, divide the distance by the spacing, round up and add one.
- Multiply number by cutting length to get total length, then by weight per metre.
- Add up the weight for each diameter.
- Have a second person check the schedule against the drawing before any steel is cut.
Bend Deductions and Hooks: Three Things People Mix Up
Site bend deductions. When you add up outer dimensions, you get a length slightly longer than the bar you need, because a bent bar cuts the corner. A widely used site convention deducts 1d for a 45 degree bend, 2d for a 90 degree bend and 3d for a 135 degree bend, where d is the bar diameter. Treat this as a working convention and confirm it for your project.
Hook and bend allowances in IS 2502. Table II of the code gives the extra length for a standard hook or bend that anchors the end of a bar. For mild steel, for example, it takes the hook allowance as 9d and the bend allowance as 5d, rounded to the nearest 5 mm and not less than 75 mm. The code dates from 1963 and its table is written around the steels of that time.
Anchorage value in IS 456. This is a design figure that counts towards development length: 4d for each 45 degrees of bend, up to 16d, and 16d for a standard U type hook. It is not a cutting length.
For stirrups and ties, IS 456 accepts a 90 degree bend followed by at least 8 diameters of straight bar, a 135 degree bend followed by at least 6, or a 180 degree bend followed by at least 4. IS 2502 asks for a straight length of at least 8 diameters beyond the curve. Earthquake resistant detailing has its own requirements, so follow the drawing.
Unit Weight of Steel Bars
Using d × d / 162.2, the weight in kg per metre is about:
- 8 mm: 0.395
- 10 mm: 0.617
- 12 mm: 0.888
- 16 mm: 1.578
- 20 mm: 2.466
- 25 mm: 3.853
Worked Example 1: Beam Stirrup
Assume a beam 230 mm wide and 450 mm deep, 30 mm nominal cover, 8 mm stirrups with 135 degree hooks, a hook extension of 10d (a common site allowance) and 150 mm spacing over a length of 4,000 mm.
- Outer width: 230 - 2 × 30 = 170 mm
- Outer depth: 450 - 2 × 30 = 390 mm
- Perimeter: 2 × (170 + 390) = 1,120 mm
- Two hook extensions: 2 × 10 × 8 = 160 mm
- Deductions: three 90 degree bends at 16 mm each and two 135 degree bends at 24 mm each, 96 mm in total
- Cutting length: 1,120 + 160 - 96 = 1,184 mm, rounded up to 1,200 mm
- Number of stirrups: 4,000 / 150 = 26.67, so 27 spaces and 28 stirrups
- Total length: 28 × 1.2 = 33.6 m
- Weight: 33.6 × 0.395 = about 13.3 kg
Worked Example 2: Footing Bars
Assume a footing 1,500 mm × 1,500 mm, 50 mm cover, 12 mm bars at 150 mm spacing in both directions, with each end turned up 200 mm as shown on the drawing.
- Horizontal length: 1,500 - 2 × 50 = 1,400 mm
- Two upturned ends: 2 × 200 = 400 mm
- Deductions: two 90 degree bends at 24 mm each, 48 mm in total
- Cutting length: 1,400 + 400 - 48 = 1,752 mm, rounded up to 1,775 mm
- Bars in each direction: the outer bar centres are 1,388 mm apart. 1,388 / 150 = 9.25, so 10 spaces and 11 bars
- Total number: 22 bars
- Total length: 22 × 1.775 = 39.05 m
- Weight: 39.05 × 0.888 = about 34.7 kg
To keep the arithmetic simple, both layers use the same length here. On site, check whether the upper layer needs a different upturn.
Plan the Cutting
Straight bars are commonly supplied in 12 m lengths. Ignoring cutting loss, one such bar gives ten pieces of 1,200 mm with nothing left over, or six pieces of 1,775 mm with 1,350 mm spare. Use the spare pieces for shorter bar marks of the same diameter before you cut a new bar.
Also check how your contract measures steel for payment, because the quantity you cut and the quantity you can bill may not be the same.
Common Mistakes
- Working from an old revision of the drawing.
- Measuring cover to the centre of the bar instead of to its outer face.
- Forgetting the bend deductions.
- Counting spaces and forgetting to add one bar.
- Treating hook allowance, bend deduction and anchorage value as the same thing.
- Leaving out laps and chairs.
- Cutting before anyone has checked the schedule.
A note on the codes: this guide refers to IS 2502:1963 and IS 456:2000. IS 456 has been amended since it was published, so use the current version with its amendments.
Learning BBS With a Course
Protrainy's Billing Estimation BBS Combo covers quantity estimation, rate analysis, survey and layout, billing and bar bending schedules, according to its page. It is taught in Hinglish, listed at Rs 15,998 and currently available at 50% off for Rs 7,999, and rated 4.9 out of 5. Before you pay, ask for the titles of the 19 lectures and how the sessions are delivered, because the page mentions both self-paced and instructor-led learning.
For more on the course and the job it leads to, see our guide to the quantity surveying, billing and BBS course. If you are a student looking for site experience, read how to find a civil engineering internship.
Next Step
Take one beam or footing from a drawing you have, prepare its schedule by hand and ask a site or billing engineer to check it. The first one is slow, and each one after it gets quicker. For any question, write to support@protrainy.com.